Summer 2026 Projects

The NMCUSD Facilities and Maintenance Department is proud to oversee multiple projects happening across our district. This page is designed to keep you informed with the latest updates and progress on projects for Summer 2026.

Summer 2026 Facilities Updates

nmcusd facilities update summer 2026
summer facilities projects: Elkhorn Elementary Repair portable restroom facilities. Repair and replace walls and boards throughout campus as needed. Parking lot expansion. Estimated completion: August 7, 2026.
Castroville Elementary Replace and install entry gate and fencing to enhance campus security. Estimated completion: July 31, 2026. Cost: TBD
summer 2026 facilities projects for echo valley: Echo Valley Elementary Install Entry Gate at Parking Lot. Estimated completion: August 7, 2026. Cost: $67,500
Prunedale Elementary Install drainage system behind Rooms 15–18. Estimated completion: July 3, 2026. Remediation of Rooms 17 and 18. Estimated completion: July 10, 2026. Replace portable ramps to address safety concerns. Repair and replace walls and boards throughout campus as needed. Overall summer work completion: August 7, 2026.
summer 2026 projects : NMC Middle School Exterior painting throughout campus as needed. Carpet replacement prioritized by need. Repair flooring and stairs in the two-story modular building to address slippery surface safety concerns. Estimated completion: August 7, 2026.
summer 2026 facilities projects: NMC High School Pressure washing of the school exterior. Forum refresh, including epoxy flooring and interior painting. Replacement of flooring in Building C-300. Estimated completion: August 7, 2026.
summer 2026 facilities projects:Central Bay Fence Repair Permanent Entrance Perimeter Privacy Play Fields Improvement Estimated completion: August 7, 2026.